Great to have accompanied Teréga for another HDD project successfully completed this week in Sauternes. The 350-metre-long DN200 pipe passed under a protected natural area and through fractured limestone crags in the heart of the region’s vineyards.
OPTIMUM engineers worked with Teréga from design and feasibility (G1 PGC, G2 PRO) and throughout the 3-week drilling operations (G4), to ensure breakouts were avoided and the agricultural land preserved.
Mission accomplished, on time and on budget.