River, Canal, Rail, Road: Four obstacles, One HDD Challenge

5 Nov 2026 | Electricity

Contributing to France’s decarbonization strategy means taking on exceptional technical challenges.

A priority trenchless project for RTE – just finished in eastern France – had it all: a river, a canal, a road, high-speed rail lines and wetlands… all on the same drill path.

With only a few months to develop the solution, the constraints were tough:

    • Inaccessible wetland on the western side
    • A drinking water catchment area on the eastern side
    • An 8-week window to complete the works, with no possibility of extension or delay

After assessing six scenarios, the selected solution was a 348-meter-long HDD crossing, designed with casings on each end, an intersect under the canal and a geomembrane to isolate the drilling operation from the drinking water. With drilling beneath railways, safety remains the highest priority:

    • 24/7 onsite monitoring by OPTIMUM engineers during drilling works under the tracks
    • Continuous control of drilling pressures and drilling fluid returns
    • Real-time monitoring of railway platform stability

When unexpected ground behaviour was detected, our response was immediate: more people, more modelling, more analysis, additional alert systems, and constant dialogue with both RTE and the SNCF to support our client in making informed decisions without compromising safety.

A great example of what HDD projects are really about. Not just drilling. Solving problems, giving technical expertise, and keeping critical infrastructure moving safely.

Learn more …

Our projects in the electricity sector

Horizontal Directional Drilling (HDD)

Horizontal Directional Drilling (HDD) offers the advantage of being quick to implement and cost-effective.

OPTIMUM services

Expertise and experience for all trenchless projects