OPTIMUM solution for ENEDIS

16 Jun 2022 | Electricity

Proud to have made it possible this week for ENEDIS to complete the missing link in reinforcing the electricity supply in Deauville, northern France. The project had been blocked for several years until OPTIMUM were called upon to solve the problem less than 12 months ago.

OPTIMUM engineers completely redesigned the trenchless project, filed a new SNCF dossier and handled negotiations to ensure all concerns were addressed and authorisations obtained to safely cross under the Lisieux to Deauville and Deauville to Cabourg railway lines, the River Touques as well as the D27A road.

OPTIMUM then supervised drilling operations 24h/24h during the construction of 2 parallel 150-metre-long HDD crossings, successfully executed by FNO, as well as continuous monitoring of both the rail platform (by ARKOGEOS) and the topography (by Lynx+). ENEDIS can now install and connect its cables to the grid.

Mission accomplished thanks to great teamwork with ENEDIS, SNCF, FNO, LYNX +, ARKOGEOS and DR.

Learn more …

Our projects in the electricity sector

Horizontal Directional Drilling (HDD)

Horizontal Directional Drilling (HDD) offers the advantage of being quick to implement and cost-effective.

OPTIMUM services

Expertise and experience for all trenchless projects